When a designer draws a gravity sewer network, they almost automatically picture open-cut excavation: an open trench along the whole street, shoring, pipes laid on a sand bed, backfill, compaction and road reinstatement. The reason is simple: in a gravity network, wastewater flows only because of the slope, and many people believe horizontal directional drilling cannot deliver the precision needed. In reality, with the right equipment and method, gravity mains can be installed by HDD, with the grade tracked in 0.01% steps.
Why the grade matters so much
In a pressure pipe, water is pushed by a pump and can rise and fall with the terrain. In a gravity main, wastewater flows only because every point of the pipe is slightly lower than the one before. The designer picks the grade so that the flow velocity is high enough for self-cleansing – so that sediment does not settle.
If a section has a stretch where the pipe rises instead of falling – a reverse grade – or a flat stretch, water stagnates there and deposits build up. Over time the cross-section shrinks, odours appear and, eventually, blockages. At small grades of a few per mille, a deviation of a few centimetres over tens of metres is enough to cause this problem. That is why the tolerance on a gravity bore is far stricter than on any other network.
What "0.01% steps" means
Grade is expressed as a percentage: 1% means a fall of 1 cm per metre, or 1 m per 100 m. A grade of 0.5% means 5 mm per metre. When we say we track the grade in 0.01% steps, it means the guidance system reads, and lets us correct, the pitch of the drill head with a resolution of one hundredth of a per cent – a difference of 0.1 mm per metre. That resolution is what makes the small grades used in flat areas achievable.
How a gravity main is installed by drilling
1. We start from the design
The starting data are the longitudinal profile, the manhole invert levels, and the pipe material and diameter. For each manhole-to-manhole section we set the entry point, the depth and the grade to follow. Where possible, the bore starts right from the manhole pit or from a nearby work pit.
2. The pilot bore – the critical stage
The whole precision of the job is decided during the pilot bore. The drill head is read continuously and its pitch is compared with the design grade. Corrections are made on the go, in small steps, so that the path does not "snake" in profile. The advance rate is slower than on an ordinary bore, because here precision matters, not metres per hour.
3. Reaming and pullback
After the pilot, the hole is reamed to the required diameter and the pipe is pulled between manholes. Reaming must be done carefully, with drilling fluid suited to the ground, so that the reamer follows the pilot path faithfully and does not drift in softer ground.
4. Verification and as-built profile
At the end we hand over the as-built profile, with levels measured along the route. This document goes into the handover file and shows, point by point, that the design grade has been met.
Which materials are used
For gravity mains installed by drilling, PE pipes are generally used: they can be butt-fused into a single string and pulled with no joints along the drilled section. Depending on the design, other materials approved for pullback can also be used. The choice is made together with the designer, taking into account diameter, depth and the water utility's requirements.
Benefits for the client and the community
- Streets stay open. Residents keep access to their homes, and buses and emergency vehicles move normally.
- No asphalt to reinstate. In a town where streets have recently been upgraded, this is often the biggest saving.
- Great depths without shoring. In flat areas, mains quickly reach 4–6 m. An open excavation at these depths needs trench support and often dewatering. Drilling avoids both.
- Fewer site risks. With no long, deep open excavations, the risk of collapse and accidents drops considerably.
- Shorter schedules. A section between two manholes can be completed in a single day.
When the method is a good fit
Gravity sewers by drilling are an excellent solution for paved streets, densely built areas, crossings along the sewer route and great depths. For very short sections at shallow depth in open ground, open-cut excavation may still be more economical. It is best to assess this at design stage, when the route and manhole positions can still be adapted to drilling.
What the design should include for a drilled installation
For a gravity main to be drilled without surprises, the design should include a few essentials. First, the complete longitudinal profile, with ground levels, manhole invert levels and the grade of each section. Second, the positions of existing utilities – water, gas, cables, fibre – because the bore must avoid them without losing grade. Third, geotechnical information: the type of ground and the water table affect the drilling fluid recipe and the number of reaming passes.
It also helps to think about manhole spacing with drilling in mind. Very long sections at very small grades demand higher precision, and very short sections reduce the advantage of the method. A conversation between designer and contractor at design stage resolves most of these points before they become site problems.
Common mistakes
- Ruling the method out from the start just because "that's how it's always been done", without a total-cost comparison.
- Ignoring existing utilities in the design, forcing route changes during execution.
- No as-built profile at handover – without it, the operator has no proof that the grade was met.
The alternative for very flat areas: vacuum sewers
Where the ground is very flat and a gravity network would need great depths or many pumping stations, an alternative is a vacuum sewer. The pipes run under negative pressure and the route can follow the terrain in a "saw-tooth" profile. PRO DRILL is currently installing such a network in Otopeni, about 15,000 m long, alongside 2,400 m of DN 280 pressure sewer – all without open-cut excavation.
Are you a designer or contractor with a gravity network in your project? Send us the longitudinal profile and we will tell you which sections can be drilled.